High-build epoxy coating a solution for lift stationProblem:A Florida utility needed to coat a concrete lift station/wet well. The structure measured 21 by 21 feet and contained two tanks. The city was searching for a solution to line and protect the structures effectively before the typical 30-day concrete cure time.
Solution:Universal Painting Corp. was able to deliver the desired solution using Epoxytec products. Mortartec Ceramico was applied at 1/4-inch minimum thickness. The product was kept under humid conditions while curing and away from direct sunlight to avoid dry-out conditions. CPP Sprayliner was applied as a protective topcoat.
Result:The application qualities of Epoxytec allowed the project to be completed